4406 HWY 14, New Iberia, LA 70560
phone:  (337)-364-5841  fax:  (337)-367-2888

email:  meredith@javeler.com

Home About Us Contacts Dredging Equipment Dredging Projects Dredging Services Newsletter

Specialty Dredging

Home
About Us 
Contacts
Dredging Equipment
Dredging Services
Dredging Projects
Barge Unloading
Upland Disposal Sites
Barge Loading & Unloading
Deep Water Dredging
    4700 Feet Deep
Stuck jack up leg
  Environmental Dredging
    Contaminated Sediment
    Wetland Restoration
   
Burying live gas pipeline
    Filling Geotubes
Offshore Dredging
Uncover buried jack up leg
Drilling Rigs
    Pipeline Burial & Retrieval
    Burying live gas pipeline
Deep Water Dredging
Maintenance Dredging  
Dredging at Ports
Marine Terminals
Dock Frontage Dredging
Dredging for Neighborhoods
Specialty Dredging
Hazardous Material
Dredging To New Depths
Sand & Gravel Excavation
Jetty& Beach Nourishment
Sediment Removal at Dams
    Small Spaces
    Bridge Construction
Newsletter 
   

Filling Coffer Dams

Javeler's 150 hp submersible agitator dredge pump is being used in Costa Rica to fill coffer dams.  Sand from the sea floor is being pumped into coffer dam.

       

 


Javeler Construction at work on Hylebos waterway
Dredgers in, poisons out....


"Along the bank of the Hylebos Waterway in Tacoma, Washington 32,000 cubic yards of contaminated sediment is being removed and treated, including some of the most dangerous chemicals in the Commencement Bay.

Javeler was selected as the preferred contractor due to our 20+ years of experience dredging with the Toyo submersible dredge pumps. The Toyo submersible dredge pump was specified as the preferred method of dredging due to the limited turbidity created when dredging as well as the high solids content when submerged in material. The treatment costs are considerable, so the focus is dredging at the highest solids content possible. Material is being pumped 2,000 feet to a treatment/dewatering process.  The sediment is then trucked to a disposal site.

Javeler is using a Manson derrick where a Toyo 8 inch submersible agitator dredge pump is hung from a crane.   A Trimble GPS system is mounted on the end of the crane to control the dredge pump location.   A Trimble depth sensor provides accurate depth measurement.  A magnetic flow meter/density meter provides percent solids and production numbers.  An electronic tide gauge corrects for tides.  All info is sent to the laptop computer in the operators cab.  A Trimble dredge software package takes all the data and displays live readouts/contours/3D visualization of what we are doing under water.    Progress surveys are completed on a regular basis with multibeam dual frequency GPS equipment to confirm dredging results. "

Dredging Hazordous waste     Dredging contaminated sediment    Actively dredging    Dredging Hazordous waste  

 Toyo pump Dredging hose.jpg (488213 bytes)    dredging contaminated sediment    Toyo Pump    Dredging software
Please Click on Thumbnail Photo to Enlarge!

Dredging To New Depths

One of our clients was working on a tension leg platform (TLP) drilling rig 150 miles offshore in the Gulf of Mexico and came to Javeler looking for a dredging system to remove mud inside of 7' diameter anchor piles in 4700 feet of water.

We modified a standard Toyo hydraulic submersible agitator pump with the addition of accumulators filled with oil for pressure equalization. Javeler designed and fabricated an independent support structure that was positioned on top of the pile. A hydraulic winch on the structure lowered the pump down 20' inside the pile and excavated the sediment. The slurry was discharged just outside the pile. A hydraulic jet pump, also on the structure, provided flow to the jet ring on the Toyo dredge pump to assist in cleaning the inside of the pile. All equipment was run hydraulically from a ROV.

   Deep dredging dredging anchor piles anchor piles dredging offshore dredging offshore dredging


 

Jetty Construction for Beach & Channel Preservation

A Toyo DP-150B is being used for Jetty Construction in New Jersey.

    jetty construction    jetty construction
Please Click on Thumbnail Photo to Enlarge!

OC Fisher Dam Dredging Project

Javeler's dredging system excavating sediment from the face of a dam in San Angelo, Texas. This joint venture with Stolt Comex Seaway, used a TOYO 10inch pump hung from a 40 ton crane mounted on a flexifloat barge.  Pumped into a 10 x 10 booster then through 4,300 feet of high density polyethylene pipe to disposal site.

Dredging at dams           dredging at dams
Please Click on Thumbnail Photo to Enlarge!

Hydraulic Dredging from Shore

Javeler removed 500,000 yards of material to create a marina and waterfront development in South Texas.

Hydraulic Dredging    marina and waterfront dredging
Please Click on Thumbnail Photo to Enlarge!

Need to Dredge in Tight Spaces!!!!

Javeler designed and supplied an 8 inch submersible agitator dredge pump system to a marine contractor on a new bridge construction project on the Mississippi river.  Sand and silt down to minus 45 feet was dredged and disposed outside the coffer dam.  Due to the tight constraints of the job and to minimize on site problems the jet hose and dredge pump electrical cable were contained inside small diameter pipes mounted on either side of the main 8" discharge line. 

Dredging Coffer Dam     Dredging Bridge Construction     Coffer Dam dredging     Dredge pump discharge            
Please Click on Thumbnail Photo to Enlarge!

Bridge Construction - Dredge Sand Inside Caisson

A 75 horsepower submersible agitator dredge pump was used to dredge out sand from inside 15  foot diameter caissons on a bridge construction project on the Mississippi river.   The 8 inch pump was hung from a crane and removed sand down to minus 20'.  Heavy slurry was pumped up through 60' of steel pipe and discharged over the side.  Compared to clam shell excavation, the hydraulic dredging method increased production, was quieter and had a much lower risk of injury or damage.

Dredging Bridge Construction        Dredging out caissons        low turbidity dredging
Please Click on Thumbnail Photo to Enlarge!

Coffer Dam Excavation
Dredged out a coffer dam at 80 foot depth using a TOYO 8 inch system.

coffer dam excavation          coffer dam excavation
Please Click on Thumbnail Photo to Enlarge!

Pump in a box - Dredging in South Texas

Toyo Pump Pump in box Dredging in a box Dredging in texas
Meredith Cross Oubre
Copyright © 2007 [Javeler Construction Co., Inc]. All rights reserved.
Information in this document is subject to change without notice.
Other products and companies referred to herein are trademarks or registered trademarks of their respective companies or mark holders.